CIVIL ENGINEERING DESIGN | CIVIL ENGINEERING DEGREE RESOURCES | CIVIL ENGINEERING DESIGN | CIVIL ENGINEERING TUTORIALS | STRUCTURAL DESIGN | CONSTRUCTION | TUTORIALS ON STRUCTURAL ENGINEERING | CONCRETE DESIGN | TIMBER DESIGN | STEEL DESIGN | BRIDGE ENGINEERING | ENVIRONMENTAL | HYDRAULICS | MATERIALS
Monday, October 29, 2012
SPECIALTY CONTRACTORS IN CIVIL ENGINEERING PROJECTS BASIC INFORMATION AND TUTORIALS
A specialty contractor or subcontractor is a separate contractor hired by the prime contractor to perform certain portions of the work. The amount of work that the prime contractor will subcontract varies from project to project.
Some federal and state regulations limit the proportion of a project that may be subcontracted, but this is rarely the case in private work. There are advantages and disadvantages to using specialty contractors.
Trades such as plumbing, electrical, and heating and air-conditioning have a tradition of being performed by specialty contractors, due to their specialized nature and licensing requirements. However, specialty contractors can now be found who are capable of performing every aspect of the construction project.
Contractors today can construct entire projects without having any direct-hire craft personnel. The use of specialty contractors has gained popularity as a means to reduce risk and overhead; however, the contractor gives up a substantial amount of control when subcontracting the entire project.
If specialty contractors are to be used, the contractor must be certain to notify them early in the bidding period so that they have time to prepare a complete, accurate proposal. If rushed, the specialty contractor tends to bid high just for protection against what might have been missed.
The use of specialty contractors can be economical, but estimates still must be done for each portion of work. Even if the estimator intends to subcontract the work, an estimate of the work should be prepared. It is possible that the estimator will not receive proposals for a project before the bid date and will have to use an estimated cost of the work in totaling the proposal.
All subcontractors’ proposals are compared with the estimator’s price; it is important that a subcontractor’s price is neither too high nor too low. If either situation exists, the estimator should call the subcontractor and discuss the proposal with him.
The specialty contractor’s proposal is often phoned, faxed, or e-mailed into the general contractor’s office at the last minute because of the subcontractor’s fear that the contractor will tell other subcontractors the proposal price and encourage lower bids. This practice is commonly referred to as bid peddling or bid shopping and is highly unethical and should be discouraged.
To prevent bid shopping, specialty contractors submit their final price only minutes before the bids close, which leads to confusion and makes it difficult for the estimator to analyze all bids carefully. This confusion is compounded by specialty contractors who submit unsolicited bids. These bids come from specialty contractors who were not contacted or invited to submit a bid, but who find out which contractors are bidding the project and submit a bid.
Since these companies are not prequalified, there is an element of risk associated with accepting one of these bids. On the other hand, not using low bids from unsolicited subcontractors places the contractor at a price disadvantage.
In checking subcontractor proposals, note especially what is included and what is left out. Each subsequent proposal may add or delete items. Often the proposals set up certain conditions, such as use of water, heat, or hoisting facilities. The estimator must compare each proposal and select the one that is the most economical.
All costs must be included somewhere. If the subcontractor does not include an item in the proposal, it must be considered elsewhere. A tricky task for the prime contractor is the comparison of the individual subcontractor’s price quotes.
Throughout the estimating process, the prime contractor should be communicating with the specific subcontractors concerning the fact that they will submit a price quote and what scope of work is to be included within that quote. However, subcontractors will include items that they were not asked to bid and will exclude items that they were asked to bid.
A “bid tabulation” or “bid tab” is used to equalize the scope between subcontractors so that the most advantageous subcontractor’s bid can be included in the prime contractor’s bid.
Tuesday, October 9, 2012
MECHANICAL PROPERTIES OF ALUMINIUM AND ALUMINIUM ALLOYS
The compositional specifications for
wrought aluminium alloys are now internationally agreed throughout
Europe, Australia, Japan and the USA. The system involves a
four-digit description of the alloy and is now specified in the UK as
BS EN 573, 1995.
Registration of wrought alloys is
administered by the Aluminum Association in Washington, DC.
International agreement on temper designations has been achieved, and
the standards agreed for the European Union, the Euro-Norms, are
replacing the former British Standards.
Thus BS EN 515. 1995 specifies in more
detail the temper designations to be used for wrought alloys in the
UK. At present, there is no Euro-Norm for cast alloys and the old
temper designations are still used for cast alloys.
In the following tables the four-digit
system is used, wherever possible, for wrought materials.
Alloy designation system for wrought
aluminium
The first of the four digits in the
designation indicates the alloy group according to the major alloying
elements, as follow:
1XXX aluminium of 99.0% minimum
purity and higher
2XXX copper
3XXX manganese
4XXX silicon
5XXX magnesium
6XXX magnesium and silicon
7XXX zinc
8XXX other element, incl. lithium
9XXX unused
1XXX Group:
In this group the last two digits
indicate the minimum aluminium percentage.
Thus 1099 indicates aluminium with a
minimum purity of 99.99%. The second digit indicates modifications in
impurity or alloying element limits. 0 signifies unalloyed aluminium
and integers 1 to 9 are allocated to specific additions.
2XXX-8XXX Groups:
In these groups the last two digits are
simply used to identify the different alloys in the groups and have
no special significance. The second digit indicates alloy
modifications, zero being allotted to the original alloy.
National variations of existing
compositions are indicated by a letter after the numerical
designation, allotted in alphabetical sequence, starting with A for
the first national variation registered.
Monday, October 8, 2012
SOURCES OF ESTIMATING INFORMATION FOR CIVIL ENGINEERING PROJECTS
For matters relevant to estimating and
costs, the best source of information is your historical data. These
figures allow for the pricing of the project to match how the company
actually performs its construction.
This information takes into account the
talent and training of the craft personnel and the management
abilities of the field staff personnel. In addition, it integrates
the construction companies’ practices and methodologies.
This is why a careful, accurate
accounting system combined with accuracy in field reports is so
important. If all of the information relating to the job is tracked
and analyzed, it will be available for future reference.
Computerized cost accounting systems
are very helpful in gathering this information and making it readily
available for future reference. See Construction Accounting and
Financial Management by Steven J. Peterson for more information on
managing construction accounting systems.
There are several “guides to
construction cost” manuals available; however, a word of extreme
caution is offered regarding the use of these manuals. They are only
guides; the figures should rarely be used to prepare an actual
estimate.
The manuals may be used as a guide in
checking current prices and should enable the estimator to follow a
more uniform system and save valuable time. The actual pricing in the
manuals is most appropriately used in helping architects check
approximate current prices and facilitate their preliminary estimate.
In addition to these printed guides,
many of these companies provide electronic databases that can be
utilized by estimating software packages. However, the same caution
needs to be observed as with the printed version.
These databases represent an average of
the methodologies of a few contractors. There is no simple way to
convert this generalized information to match the specifics of the
construction companies’ methodologies.
Sunday, October 7, 2012
TYPES OF BIDS IN CIVIL ENGINEERING PROJECTS BASIC INFORMATION
Basically, the two bidding procedures
by which the contractor gets to build a project for owners are as
follows:
1. Competitive bidding
2. Negotiated bidding
Competitive bidding involves each
contractor submitting a lump-sum bid or a proposal in competition
with other contractors to build the project. The project may be
awarded based on the price or best value.
When the project is awarded based on
the price, the lowest lump-sum bidder is awarded the contract to
build the project as long as the bid form and proper procedures have
been followed and this bidder is able to attain the required bonds
and insurance.
When the project is awarded based upon
the best value, the proposals from the contractors are rated based on
specified criteria with each criterion given a certain percentage of
the possible points. The criteria may include review of the
capabilities of the assigned project team, the company’s
capabilities and its approach to the project (including schedule),
proposed innovation, method of mitigating risk, and price.
The price is often withheld from the
reviewers until the other criteria have been evaluated to prevent the
price from affecting the ratings of the other criteria. Most
commonly, the bids must be delivered to the person or place specified
by a time stated in the instruction to bidders.
The basic underlying difference between
negotiated work and competitive bidding is that the parties arrive at
a mutually agreed upon price, terms and conditions, and contractual
relationship. This arrangement often entails negotiations back and
forth on virtually all aspects of the project, such as materials
used, sizes, finishes, and other items that affect the price of the
project.
Owners may negotiate with as many
contractors as they wish. This type of bidding is often used when
owners know which contractor they would like to build the project, in
which case competitive bidding would waste time.
The biggest disadvantage of this
arrangement is that the contractor may not feel the need to work
quite as hard to get the lowest possible prices as when a competitive
bidding process is used.
Saturday, October 6, 2012
OVERVIEW OF EARTHQUAKE RISK CIVIL ENGINEERING CONTEXT BASIC INFORMATION AND TUTORIALS
The first step in understanding
earthquake risk is to dissect the earthquake risk or loss process
into its constituent steps. Earthquake risk begins with the
occurrence of the earthquake, which results in a number of earthquake
hazards.
The most fundamental of these hazards
is faulting, that is, the surface expression of the differential
movement of blocks of the Earth’s crust. Faulting can be a simple
“mole-track” lateral movement, or a major vertical scarp, or may
not even be visible.
In most cases, faulting is typically a
long narrow feature, and therefore affects a relatively small
fraction of the total affected structures and persons. Affecting a
much greater number of structures and persons is shaking, which is
typically the primary hazard due to earthquakes.
Depending on the earthquake,
liquefaction, other forms of ground failure, tsunamis, or other types
of hazards may be significant agents of damage. For various reasons,
many buildings, portions of the infrastructure, and other structures
cannot fully resist these hazards, and sustain some degree of damage.
Primary damage can vary from minor
cracking to total collapse. Some building types are more vulnerable
than others, but even when a building sustains no structural damage,
the contents of the building may be severely damaged.
For certain occupancies, such as
hospitals or emergency services dispatch centers, this damage to
contents (laboratories, specialized machinery, communication
equipment, etc.) can be very important. Additionally, these various
kinds of primary damage can lead to other secondary forms of hazard
and damage, such as releases of hazardous materials, major fires, or
flooding.
Damage results in loss.
Primary loss can take many forms —
life loss or injury is the primary concern, but financial loss and
loss of function are also of major concern. The likelihood of
sustaining a loss is termed risk . Primary losses lead to secondary
forms of loss, such as loss of revenues resulting from business
interruption and loss of market share and/or reputation.
QUANTITY ESTIMATING CIVIL ENGINEERING PROJECTS BASIC INFORMATION AND TUTORIALS
In Canada, parts of Europe, and on most
road construction projects in the United States, the estimated
quantities of materials required on the project are determined by a
professional quantity surveyor or engineer and provided to the
interested bidders on the project.
This is often referred to as a unit
price bid. In this method of bidding, the contractors are all bidding
based on the same quantities, and the estimator spends time
developing the unit prices. For example, the bid may be $47.32 per
cubic yard (cy) of concrete.
Because all of the contractors are
bidding on the same quantities, they will work on keeping the cost of
purchasing and installing the materials as low as possible.
As the project is built, the actual
number of units required is checked against the original number of
units on which the estimates were made. For example, the original
quantity survey called for 715 linear feet (lf) of concrete curbing.
If 722 lf were actually installed, then
the contractor would be paid for the additional 7 lf. If 706 lf were
used, then the owner would pay only for the 706 lf installed and not
the 715 lf in the original quantity survey.
This type of adjustment is quite
common. When errors do occur and there is a large difference between
the original quantity survey and the actual number of units, an
adjustment to the unit price is made. Small adjustments are usually
made at the same unit rate as the contractor bid.
Large errors may require that the unit
price be renegotiated. If the contractor is aware of potential
discrepancies between the estimated quantities and those that will be
required, the contractor may price his or her bid to take advantage
of this situation.
With a belief that the estimated
quantities are low, the contractor may reduce his or her unit price
to be the low bidder. If the assumption is true, the contractor has
the potential to make the same profit by distributing the project
overhead over a greater number of units.
Subscribe to:
Comments (Atom)
CONSTRUCTION MANAGEMENT - Case study: Stoke-on-Trent Schools, UK
In 1997 many of the schools in Stoke-on-Trent were in a dilapidated state and not fit for modern teaching and learning practice. The school...