What Are The Usual Problem In
Concrete Finishing?
The skill required by carpenters to
make and erect form work for concrete is seldom fully appreciated.
The formwork must remain ‘true to line and level’ despite
substantial loading from the wet concrete. Column and wall faces have
to be strictly vertical, and beam soffits strictly level, or any
departure will be easily visible by eye.
Formwork for concrete which is to
remain exposed to view has to be planned and built as carefully as if
it were a permanent feature of the building. Many methods have been
tried to make the appearance of exposed concrete attractive: but any
of them can be ruined by honeycombing, a bad construction joint, or
by subsequent weathering revealing that one pour of concrete has not
been identical with adjacent pours, or that the amount of vibration
used in compacting one panel has been different from that used in
others.
If concrete has to remain exposed to
public view, then the resident engineer should endeavour to agree
with the contractor what is the most suitable method for achieving
the finish required if the specification or drawings do not give
exact guidance on the matter. The problem is that if, through lack of
detailed attention, a ‘mishap’ on the exposed surface is revealed
when the formwork is struck, it is virtually impossible to rectify
it.
Sometimes rendering the whole surface
is the only acceptable remedy. Where concrete will not remain exposed
to view, minor discrepancies can be accepted. ‘Fins’ of concrete
caused by the mix leaking through butt joints in the formwork should
be knocked off. Shallow honeycombing should be chiselled out, and a
chase cut along any defective construction joint.
The cut-out area or chase should be
washed, brushed with a thick cement grout, and then filled with a
dryish mortar mix. This rectifying work should be done as soon as
possible so the mortar mix has a better chance of bonding to the
‘green’ concrete.
Shrinkage cracking of concrete is a
common experience. The shrinkage of concrete due to drying is of the
order of 0.2–0.5mm/m for the first 28 days. Subsequently concrete
may expand slightly when wet and shrink on drying.
The coefficient of temperature
expansion or contraction is very much smaller, of the order of
0.007mm/m per degree centigrade of change. Rich concrete mixtures
tend to shrink more than lean mixes. The use of large aggregate, such
as 40 mm instead of 20 mm, helps to minimize shrinkage. To avoid
cracking of concrete due to shrinkage, wall lengths of concrete
should be limited to about 9 m if restrained at the base or ends.
Heavy foundations to a wall should not
be allowed to stand and dry out for a long period before the wall is
erected, because the wall concrete bonding to the base may be unable
to shrink without cracking. Concrete is more elastic than is commonly
appreciated, for example the unrestrained top of a 300 mm diameter
reinforced concrete column 4m high can be made to oscillate through
nearly 1 cm by push of the hand.








