A pile is a slender column made of
wood, concrete or steel. A pile is either driven into the soil or
formed in situ by excavating a hole and then filling it with
concrete. A group of piles are driven to the required depth and are
capped with R.C.C. slab, over which super structure is built.
The pile transfer the load to soil by
friction or by direct bearing, in the latter case, piles being taken
up to hard strata. This type of foundations is used when top soil is
not capable of taking the load of the structure even at 3–4 m
depth. Pile foundations are classified according to the materials
used and also on the nature of load transfer.
Classification According to Materials
Used:
Piles may be classified as:
(a) Timber piles
(b) Concrete piles
(c) Steel piles and
(d) Composite piles.
(a) Timber piles: Circular
seasoned wood can be used as piles. Their diameter may vary from 200
mm to 400 mm. Similarly square piles of sizes 200 mm to 400 mm are
also used. The length of timber pile should not be more than 20 times
its lateral dimension.
The bottom of the pile is sharpened and
is provided with iron shoe, so that it can be driven in the ground
easily by hammering. These piles should be always kept below water
table; otherwise alternating wet and dry condition cause the decay.
These piles are cheap and can be easily
driven rapidly. The main disadvantage is their load carrying capacity
is low and are likely to be damaged during driving in the soil.
(b) Concrete piles: These piles
may be further classified as precast piles and cast in situ piles.
Precast piles are reinforced with steel and are manufactured in
factories. The cross-section diameter/dimension varies from 200 mm to
500 mm.
Square, circular and octagonal sections
are commonly used. The length of piles may be up to 20 m. They are
provided with steel shoe at the lowest end. These piles can carry
fairly large loads. These piles are highly resistant to biological
and chemical actions of the soil. The disadvantage of these piles is
they need more time to manufacture and are heavy to handle.
Cast in situ concrete piles are formed
first by boring the holes in the soil and then concreting them.
Concreting is usually made using casing tubes. If the hole is filled
with only plain concrete it is pressure pile.
The load carrying capacity of the piles
may be increased by providing enlarged base. The reinforcement caging
may be inserted in the bored holes and to increase load carrying
capacity one or two under reams may be formed. After that concreting
may be carried out.
Such piles are known as under reamed
piles. These piles are provided at regular interval of 2 to 4 m and
capping beam is provided over them.
(c) Steel Piles: A steel pile
may be a rolled steel I sections, tubes or fabricated in the form of
box. These piles are mostly used as bearing piles since surface
available for friction is less and also the coefficient of friction
is less. If tubes are used the soil inside the tube is driven out by
compressed air and concrete is filled. These piles are very useful
for driving close to existing structures since they disturb the soil
least.
(d) Composite Piles: Composite
piles may be of concrete and timber or of concrete and steel. Wooden
piles should not be subjected to alternating wet and dry conditions.
Hence they are preferred for the portion below water table.
The portion above water table are built
with cast in situ concrete piles. If the required length of steel
piles is less than the depth of pile, many times upper portions are
built with concrete. Thus steel and concrete composite piles are
sometimes used.
Classification of Piles According to
Load Transfer:
According to the load transfer to the
soil piles may be classified as
(a) Bearing piles and
(b) Friction piles.
Bearing piles rest on hard
strata and transfer the load by bearing. Such piles are preferred.
These piles are used if the hard strata is available at reasonable
depth.
Friction piles transfer the load
to the soil by the friction between soil and the pile. Such piles are
used if hard strata is not available to a considerable depth. The
friction developed is to be properly assessed before deciding the
length of the pile. The surface of such piles is made rough to
increase the skin friction so that required length of pile is
reduced.

