Showing posts with label Bridges. Show all posts
Showing posts with label Bridges. Show all posts

ARC TYPES BRIDGES COMPARISON WITH OTHER BRIDGE TYPES


Comparison with Simple Spans.
Simple-span girder or truss construction normally falls within the range of the shortest spans used up to a maximum of about 800 ft. Either true arches under favorable conditions or tied arches under all conditions are competitive within the range of 200 to 800 ft.

(There will be small difference in cost between these two types within this span range.) With increasing emphasis on appearance of bridges, arches are generally selected rather than simple-span construction, except for short spans for which beams or girders may be used.


Comparison with Cantilever or Continuous Trusses.
The normal range for cantilever or continuous-truss construction is on the order of 500 to 1800 ft for main spans. More likely, a top limit is about 1500 ft. Tied arches are competitive for spans within the range of 500 to 1000 ft.

True arches are competitive, if foundation conditions are favorable, for spans from 500 ft to the maximum for the other types. The relative economy of arches, however, is enhanced where site conditions make possible use of relatively short-span construction over the areas covered by the end spans of the continuous or cantilever trusses.

The economic situation is approximately this: For three-span continuous or cantilever layouts arranged for the greatest economy, the cost per foot will be nearly equal for end and central spans. If a tied or true arch is substituted for the central span, the cost per foot may be more than the average for the cantilever or continuous types.

If, however, relatively short spans are substituted for the end spans of these types, the cost per foot over the length of those spans is materially reduced. Hence, for a combination of short spans and a long arch span, the overall cost between end piers may be less than for the other types. In any case, the cost differential should not be large.

Comparison with Cable-Stayed and Suspension Bridges.
Such structures normally are not used for spans of less than 500 ft. Above 3000 ft, suspension bridges are probably the most practical solution. In the shorter spans, self-anchored construction is likely to be more economical than independent anchorages.

Arches are competitive in cost with the self-anchored suspension type or similar functional type with cable-stayed girders or trusses. There has been little use of suspension bridges for spans under 1000 ft, except for some self-anchored spans.

For spans above 1000 ft, it is not possible to make any general statement of comparative costs. Each site requires a specific study of alternative designs.

SUSPENSION BRIDGE TYPES BASIC INFORMATION AND TUTORIALS


What Are The Types Of Suspension Bridges?

Several arrangements of suspension bridges are illustrated in Fig. 1. The main cable is continuous, over saddles at the pylons, or towers, from anchorage to anchorage.  


FIGURE 15.9 Suspension-bridge arrangements. (a) One suspended span, with pin-ended stiffening truss. (b) Three suspended spans, with pin-ended stiffening trusses. (c) Three suspended spans, with continuous stiffening truss. (d ) Multispan bridge, with pin-ended stiffening trusses. (e) Self-anchored suspension bridge.


When the main cable in the side spans does not support the bridge deck (side spans independently supported by piers), that portion of the cable from the saddle to the anchorage is virtually straight and is referred to as a straight backstay.

This is also true in the case shown in Fig. 1a where there are no side spans. Figure 1d represents a multispan bridge. This type is not considered efficient, because its flexibility distributes an undesirable portion of the load onto the stiffening trusses and may make horizontal ties necessary at the tops of the pylons.

Ties were used on several French multispan suspension bridges of the nineteenth century. However, it is doubtful whether tied towers would be esthetically acceptable to the general public. Another approach to multispan suspension bridges is that used for the San Francisco–Oakland Bay Bridge (Fig. 2). It is essentially composed of two three-span suspension bridges placed end to end.


This system has the disadvantage of requiring three piers in the central portion of the structure where water depths are likely to be a maximum. Suspension bridges may also be classified by type of cable anchorage, external or internal. Most suspension bridges are externally anchored (earth-anchored) to a massive external anchorage (Fig. 1a to d).

In some bridges, however, the ends of the main cables of a suspension bridge are attached to the stiffening trusses, as a result of which the structure becomes self-anchored (Fig. 1e). It does not require external anchorages.

The stiffening trusses of a self-anchored bridge must be designed to take the compression induced by the cables. The cables are attached to the stiffening trusses over a support that resists the vertical component of cable tension. The vertical upward component may relieve or even exceed the dead-load reaction at the end support. If a net uplift occurs, a pendulum link tie-down should be provided at the end support.

Self-anchored suspension bridges are suitable for short to moderate spans (400 to 1,000 ft) where foundation conditions do not permit external anchorages. Such conditions include poor foundation bearing strata and loss of weight due to anchorage submergence. Typical examples of self-anchored suspension bridges are the Paseo Bridge at Kansas City, with a main span of 616 ft, and the former Cologne-Mu¨lheim Bridge (1929) with a 1,033-ft span.

Another type of suspension bridge is referred to as a bridle-chord bridge. Called by Germans Zu¨gelgurtbru¨cke, these structures are typified by the bridge over the Rhine River at Ruhrort-Homberg (Fig. 15.11), erected in 1953, and the one at Krefeld-Urdingen, erected in 1950.  


It is a special class of bridge, intermediate between the suspension and cable-stayed types and having some of the characteristics of both. The main cables are curved but not continuous between towers. Each cable extends from the tower to a span, as in a cable stayed bridge. The span, however, also is suspended from the cables at relatively short intervals over the length of the cables, as in suspension bridges.

A distinction to be made between some early suspension bridges and modern suspension bridges involves the position of the main cables in profile at midspan with respect to the stiffening trusses. In early suspension bridges, the bottom of the main cables at maximum sag penetrated the top chord of the stiffening trusses and continued down to the bottom chord.

Because of the design theory available at the time, the depth of the stiffening trusses was relatively large, as much as 1⁄40 of the span. Inasmuch as the height of the pylons is determined by the sag of the cables and clearance required under the stiffening trusses, moving the midspan location of the cables from the bottom chord to the top chord increases the pylon height by the depth of the stiffening trusses.

In modern suspension bridges, stiffening trusses are much shallower than those used in earlier bridges and the increase in pylon height due to midspan location of the cables is not substantial (as compared with the effect in the Williamsburg Bridge in New York City where the depth of the stiffening trusses is 25% of the main-cable sag).

Although most suspension bridges employ vertical suspender cables to support the stiffening trusses or the deck structural framing directly, a few suspension bridges, for example, the Severn Bridge in England and the Bosporus Bridge in Turkey, have inclined or diagonal suspenders.

In the vertical-suspender system, the main cables are incapable of resisting shears resulting from external loading. Instead, the shears are resisted by the stiffening girders or by displacement of the main cables. In bridges with inclined suspenders, however, a truss action is developed, enabling the suspenders to resist shear.

(Since the cables can support loads only in tension, design of such bridges should ensure that there always is a residual tension in the suspenders; that is, the magnitude of the compression generated by live-load shears should be less than the dead-load tension.) A further advantage of the inclined suspenders is the damping properties of the system with respect to aerodynamic oscillations.



CLASSIFICATION OF BRIDGES BY SPAN BASIC AND TUTORIALS


Bridges have been categorized in many ways.

They have been categorized by their principal use as highway, railroad, pedestrian, pipeline, etc.; by the material used in their construction as stone, timber, wrought iron, steel, concrete, and prestressed concrete; by their structural form as girder, box-girder, moveable, truss, arch, suspension, and cable-stayed; by structural behavior as simple span, continuous, and cantilever; and by their span dimension as short, intermediate, and long-span. The last classification, specifically long-span, is the one of
primary interest in this Section.

The span of a bridge is defined as the dimension (length), along the longitudinal axis of the bridge, between two supports. However, what defines a ‘‘long-span’’? In other words, how long is long?

It should be understood that the word ‘‘long’’ is a relative term. Throughout the history of bridge construction and technology, as our methods of analysis improved and as we moved from one material to another more appropriate material, the span length has been constantly pushed forward to a new frontier.

Therefore, what was considered a long-span in the eighteenth and nineteenth centuries may not be considered as such in the twentieth century. What is considered a long-span today may not be considered as such in the twenty-first century.

It is conceptually simple to understand this concept of the relativity of span length, however, in of itself it does not define ‘‘long-span.’’

Perhaps the best definition of ‘‘long-span’’ is that presented by Silano as ‘‘if a bridge has a span too long to design from standard handbooks, you call it a long-span bridge.’’ The current AASHTO Standard Specifications for Highway Bridges states that ‘‘They apply to ordinary highway bridges and supplemental specifications may be required for unusual types and for bridges with spans longer than 500 ft.’’

Therefore, by the above criteria, the lower bound of long-span may be considered to be 500 ft, at least for highway bridges. (Silano, L. G., ‘‘Design of Long-Span Bridges,’’ reprinted from the Structural Group Lecture Series of the Boston Society of Civil Engineers/ASCE, April 1990, Parsons Brinckerhoff, New York.)

MAIN COMPONENTS OR PARTS OF SUSPENSION BRIDGES BASIC INFORMATION


Suspension bridges with cables made of high-strength, zinc-coated, steel wires are suitable for the longest of spans. Such bridges usually become economical for spans in excess of 1000 ft, depending on specific site constraints.

Nevertheless, many suspension bridges with spans as short as 300 or 400 ft have been built, to take advantage of their esthetic features. The basic economic characteristic of suspension bridges, resulting from use of high strength materials in tension, is lightness, due to relatively low dead load.

But this, in turn, carries with it the structural penalty of flexibility, which can lead to large deflections under live load and susceptibility to vibrations. As a result, suspension bridges are more suitable for highway bridges than for the more heavily loaded railroad bridges.

Nevertheless, for either highway or railroad bridges, care must be taken in design to provide resistance to wind- or seismic-induced oscillations, such as those that caused collapse of the first Tacoma Narrows Bridge in 1940.

A pure suspension bridge is one without supplementary stay cables and in which the main cables are anchored externally to anchorages on the ground. The main components of a suspension bridge are illustrated in Fig. 15.8.

Most suspension bridges are stiffened; that is, as shown in Fig. 15.8, they utilize horizontal stiffening trusses or girders. Their function is to equalize deflections due to concentrated live loads and distribute these loads to one or more main cables.

The stiffer these trusses or girders are, relative to the stiffness of the cables, the better this function is achieved. (Cables derive stiffness not only from their crosssectional dimensions but also from their shape between supports, which depends on both cable tension and loading.)

For heavy, very long suspension spans, live-load deflections may be small enough that stiffening trusses would not be needed. When such members are omitted, the structure is an unstiffened suspension bridge.

Thus, if the ratio of live load to dead load were, say, 1:4, the\ midspan deflection would be of the order of 1⁄100 of the sag, or 1/1,000 of the span, and the use of stiffening trusses would ordinarily be unnecessary. (For the George Washington Bridge as initially constructed, the ratio of live load to dead load was approximately 1:6. Therefore, it did not need a stiffening truss.)

FIGURE 15.8 Main components of a suspension bridge.

BRIDGE STEELS BASIC AND TUTORIALS

BRIDGE STEELS BASIC INFORMATION
What Are The Type Of Steels Used In Constructing Bridges?


Steels for application in bridges are covered by A709, which includes steel in several of the categories mentioned above. Under this specification, grades 36, 50, 70, and 100 are steels with yield strengths of 36, 50, 70, and 100 ksi, respectively.

The grade designation is followed by the letter W, indicating whether ordinary or high atmospheric corrosion resistance is required. An additional letter, T or F, indicates that Charpy V-notch impact tests must be conducted on the steel.

The T designation indicates that the material is to be used in a non-fracture-critical application as defined by AASHTO; the F indicates use in a fracture-critical application.

A trailing numeral, 1, 2, or 3, indicates the testing zone, which relates to the lowest ambient temperature expected at the bridge site. (see Table Below)


As indicated by the first footnote in the table, the service temperature for each zone is considerably less than the Charpy V-notch impact-test temperature.

This accounts for the fact that the dynamic loading rate in the impact test is more severe than that to which the structure is subjected.

The toughness requirements depend on fracture criticality, grade, thickness, and method of connection. A709-HPS70W, designated as a High Performance Steel (HPS), is also now available for highway bridge construction.

This is a weathering plate steel, designated HPS because it possesses superior weldability and toughness as compared to conventional steels of similar strength.

For example, for welded construction with plates over 21⁄2 in thick, A709-70W must have a minimum average Charpy V-notch toughness of 35 ft lb at 10 F in Zone III, the most severe climate.

Toughness values reported for some heats of A709-HPS70W have been much higher, in the range of 120 to 240 ft lb at 10 F. Such extra toughness provides a very high resistance to brittle fracture.

(R. L. Brockenbrough, Sec. 9 in Standard Handbook for Civil Engineers, 4th ed., F. S.
Merritt, ed., McGraw-Hill, Inc., New York.)

GENERAL APPROACHES TO FABRICATION AND ERECTION OF BRIDGE STEELWORKS BASICS AND TUTORIALS

FABRICATION AND ERECTION OF BRIDGE STEELWORKS GENERAL APPROACHES
What Are The General Approaches To Fabrication and Erection Of Bridge Steelworks


The objective in steel bridge construction is to fabricate and erect the structure so that it will have the geometry and stressing designated on the design plans, under full dead load at normal temperature.

This geometry is known as the geometric outline.

In the case of steel bridges there have been, over the decades, two general procedures for achieving this objective:

1. The “field adjustment” procedure — Carry out a continuing program of steelwork surveys and measurements in the field as erection progresses, in an attempt to discover fabrication and erection deficiencies; and perform continuing steelwork adjustments in an effort to compensate for such deficiencies and for errors in span baselines and pier elevations.

2. The “shop control” procedure — Place total reliance on first-order surveying of span baselines and pier elevations, and on accurate steelwork fabrication and erection augmented by meticulous construction engineering; and proceed with erection without any field adjustments, on the basis that the resulting bridge deadload geometry and stressing will be as good as can possibly be achieved.

Bridge designers have a strong tendency to overestimate the capability of field forces to accomplish accurate measurements and effective adjustments of the partially erected structure, and at the same time they tend to underestimate the positive effects of precise steel bridgework fabrication and erection.

As a result, we continue to find contract drawings for major steel bridges that call for field evolutions such as the following:

1. Continuous trusses and girders
— At the designated stages, measure or “weigh” the reactions on each pier, compare them with calculated theoretical values, and add or remove bearing-shoe shims to bring measured values into agreement with calculated values.

2. Arch bridges
— With the arch ribs erected to midspan and only the short, closing “crown sections” not yet in place, measure thrust and moment at the crown, compare them with calculated theoretical values, and then adjust the shape of the closing sections to correct for errors in span-length measurements and in bearing-surface angles at skewback supports, along with accumulated fabrication and erection errors.

3. Suspension bridges
— Following erection of the first cable wire or strand across the spans from anchorage to anchorage, survey its sag in each span and adjust these sags to agree with calculated theoretical values.

4. Arch bridges and suspension bridges — Carry out a deck-profile survey along each side of the bridge under the steel-load-only condition, compare survey results with the theoretical profile, and shim the suspender sockets so as to render the bridge floor beams level in the completed structure.

5. Cable-stayed bridges
— At each deck-steelwork erection stage, adjust tensions in the newly erected cable stays so as to bring the surveyed deck profile and measured stay tensions into agreement with calculated theoretical data.

There are two prime obstacles to the success of “field adjustment” procedures of whatever type: (1) field determination of the actual geometric and stress conditions of the partially erected structure and its components will not necessarily be definitive, and (2) calculation of the corresponding “proper” or “target” theoretical geometric and stress conditions will most likely prove to be less than authoritative.

STRUCTURAL DETAILER RESPONSIBILITY ON BRIDGE DESIGN

STRUCTURAL DETAILER RESPONSIBILITY
Bridge Design Tutorial


The structural detailer is responsible for the structural plan sheets. The plans shall be neat, correct, and easy to follow and drawn to scale. The structural detailer may also assist the designer and design checker in such areas as determining control dimensions and elevations, geometry, and calculating quantities.

Some detailing basics and principles:

a. Refer to BDM for detailing practices.

b. Provide necessary and adequate information. Try to avoid repetition of information.

c. Avoid placing too much information into any one sheet.

d. Plan sheets should detail in a consistent manner and follow accepted detailing practices.

e. Provide clear and separate detail of structural geometrics. Use clear detailing such as “stand alone” cross sections or a framing plan to define the structure.

f. Avoid reinforcing steel congestion.

g. Check reinforcement detail for consistency. Beware of common mistakes about placement of stirrups and ties (such as: stirrups too short, effect of skew neglected, epoxy coating not considered, etc.). Check splice location and detail, and welding locations.

h. Use cross references properly.

i. Use correct and consistent terminology. For example, the designation of Sections, Views, and Details.

j. Check for proper grammar and spelling.

k. On multiple bridge contracts, the structural detailing of all bridges within the contract shall be coordinated to maximize consistency of detailing from bridge to bridge. Extra effort will be required to assure uniformity of details, particularly if multiple design units and/or consultants are involved in preparing bridge plans. This is a critical element of good quality bridge plans.

l. Refer to the Bridge Book of Knowledge for current special features and details used on other projects.

In bridge widening projects, the method of stitching is normally employed for connecting existing deck to the new deck. What are the problems associated with this method in terms of shrinkage of concrete?

BRIDGE WIDENING USING CONCRETE BASICS AND TUTORIALS
Civil Engineering Tutorials


In the method of stitching, it is a normal practice to construct the widening part of the bridge at first and let it stay undisturbed for several months. After that, concreting will then be carried out for the stitch between the existing deck and the new deck.

In this way, the dead load of the widened part of bridge is supported by itself and loads arising from the newly constructed deck will not be transferred to the existing deck which is not designed to take up these extra loads.

One of the main concerns is the effect of stress induced by shrinkage of newly widened part of the bridge on the existing bridge.

To address this problem, the widened part of the bridge is constructed a period of time (say 6-9 months) prior to stitching to the existing bridge so that shrinkage of the new bridge will take place within this period and the effect of shrinkage stress exerted on the new bridge is minimized.

Traffic vibration on the existing bridge causes adverse effect to the freshly placed stitches. To solve this problem, rapid hardening cement is used for the stitching concrete so as to shorten the time of setting of concrete.

Moreover, the stitching work is designed to be carried out at nights of least traffic (Saturday night) and the existing bridge may even be closed for several hours (e.g. 6 hours) to let the stitching works to left undisturbed.

Sometimes, longitudinal joints are used in connecting new bridge segments to existing bridges. The main problem associated with this design is the safety concern of vehicles.

The change of frictional coefficients of bridge deck and longitudinal joints when vehicles change traffic lanes is very dangerous to the vehicles. Moreover, maintenance of longitudinal joints in bridges is quite difficult.

Note: Stitching refers to formation of a segment of bridge deck between an existing bridge and a new bridge.
electrical engineering tutorials