STRUCTURAL STEEL FABRICATION BASIC INFORMATION

When considering fabrication, as well as erection of the fabricated product, the designer must taken into account contractual matters, work by others on the construction team, schedule implications of the design, and quality assurance matters.

Fortunately, there are well established aids for these considerations. Contractual questions such as what constitutes structural steel, procedures for preparing and approving the shop detail drawings, and standard fabrication procedures and tolerances are all addressed in the AISC’s Code of Standard Practice.

Insights on economical connection details and the impact of material selection on mill material deliveries are generally available from the fabricator’s engineering staff. These engineers are also able to comment on unique erection questions.

Quality assurance questions fall into two categories, fabrication operations and field operations. Today, sound quality control procedures are in place in most fabrication shops through an AISC program which prequalifies fabricators.

There are three levels of qualification: I, II and III, with Level III being the most demanding. Fabricators with either a Level I or Level II certification are suitable for almost all building work. Most engineers incorporate the AISC’s Code of Standard Practice in their project specification.

Shop Detail Drawings
Detail drawings are prepared by the fabricator to delineate to his work force the fabrication requirements. Because each shop has certain differences in equipment and/or procedures, the fabricator develops details which, when matched with his processes, are the most economical.

To accomplish this end, the design drawings need to be complete, showing all structural steel requirements, and should include design information on the forces acting at connections. Designers should avoid specifying deck openings and beam penetrations through notes on the drawings. This is a frequent cause of extra costs on fabrication contracts.

Fabrication Processes
Mill material is cut to length by sawing, shearing, or flame cutting. Columns may also be milled to their final length. Holes for fasteners are drilled or punched. Punched and reamed holes are seldom used in building construction. Cuts for weld preparation, web openings, and dimensional clearances are flame cut.

AISC guidelines for each of these processes are associated with the AISC’s fabricator prequalification program. Welding for building construction is performed in accordance with the provisions of the AWS Structural Welding Code, D1.1. Most requirements can be satisfied using pre-qualified welding procedures.

PRECAST AND PRESTRESSED DECK SLABS BASIC AND TUTORIALS


The deck is usually the first element in a bridge to deteriorate and to require funds for rehabilitation. In situations where traffic volumes are high, it is often necessary to rehabilitate or replace the deck in sections during off-peak periods.

Because of the time required for site-cast concrete to cure, a number of replacement strategies have been developed using prefabricated deck slabs (Issa et al., 1995a,b). Most of the systems involve a transverse segment (Figure 33.11) connected to the supporting beams with a rapid-curing polymer or hydraulic cement concrete.


FIGURE 33.11 Prestressed deck slabs. (From Sprinkel, M.M., Prefabricated Bridge Elements and Systems, NCHRP Synthesis 119, Transportation Research Board, Washington, D.C., 1985.)


Shear transfer between adjacent slabs is achieved through the use of grouted keyways, site-cast concrete, and post-tensioning. Composite action is achieved through the use of studs on steel beams that extend into voided areas in the slabs that are then filled with polymer or hydraulic cement concrete.

Precast deck slabs can behave in a full-composite manner when connected to steel stringers with studs and epoxy mortar and when keyways are grouted with epoxy mortar (Osegueda et al., 1989).

An earlier study identified some suitable connection details and concluded that the deck slabs are more economical than site cast concrete because of the structural efficiency provided by post-tensioning and prestressing and because of the reduced construction time (Berger, 1983).

Improved connection details for the use of panels on steel beams and prestressed concrete beams have been developed (Tadros and Baishya, 1998).

More recently, a special loop bar reinforcement detail has been developed to provide live load distribution across transverse and longitudinal joints (see FHWA, 2004). A new full-depth precast prestressed concrete bridge deck slab system has been developed that includes stemmed slabs, transverse grouted joints, longitudinal post-tensioning, and welded threaded and headless studs (Tadros and Baishya, 1998).

The deck slabs are thinner and lighter than a conventional deck and can be constructed faster. Prestressed deck slabs typically have been used on major bridge deck replacement projects (Figure 33.12) such as the Woodrow Wilson Bridge (Lutz and Scalia, 1984).


FIGURE 33.12 Prestressed post-tensioned deck slabs were installed at night to replace the deck of the Woodrow Wilson Bridge.


Also, most replacements have involved the use of transverse slabs. The decks on the George Washington Memorial Parkway were replaced using precast longitudinally post-tensioned transverse deck slabs (Jakovich and Alvarez, 2002).

A latex-modified concrete overlay was placed over the slabs. The truss spans of the deck on I-95 in Richmond, Virginia, were recently replaced with night lane closures using the full-depth transverse deck slabs (Figure 33.13).


FIGURE 33.13 Special loop bar connection detail for deck slabs. (From FHA, Prefabricated Bridge Elements and Systems in Japan and Europe, Summary Report, International Technology Exchange Programs, Federal Highway Administration, Washington, D.C., 2004)


The slabs were also used to replace the deck on Route 50 in Fairfax County, Virginia (Babaei et al., 2001). The Virginia Department of Transportation first used transverse precast deck slabs to replace a deck on Route 235 over Dogue Creek in Fairfax County in 1981 (Sprinkel, 1982).

Longitudinal slabs were successfully used to rehabilitate the Freemont Street Bridge (Smyers, 1984), and a new bridge was built in Thailand (Zeyher, 2003).

Longitudinal, partial-depth, or full-depth deck slabs that that are precast on one or more concrete or steel beams have also been used successfully (FHWA, 2004). The superstructure elements are set next to each other and are typically connected by transverse post-tensioning in the deck and diaphragms between the beams.

Keyways in the deck are grouted. The deck on I-95 in Richmond, Virginia, was recently replaced with night lane closures using the full-depth deck slabs on steel beam superstructure elements. When partial depth deck superstructure elements are set next to each other, reinforced site-cast concrete facilitates the connection of the elements.
electrical engineering tutorials