The asphalt paving required on the
project is generally subcontracted to someone specializing in paving.
The general contractor’s estimator will make an estimate to check
the subcontractor’s price.
Asphalt paving will most commonly be
hot-mix and is generally classified by traffic (heavy, medium, or
light) and use (walks, courts, streets, driveways, etc.).
The estimator will be concerned with
subgrade preparation, subdrains, soil sterilization, insulation
course, subbase course, base courses, prime and tack coats, and the
asphalt paving required.Not all items are required on any given
project, so the estimator should determine which items will be
required, the material and equipment necessary for each portion of
the work, and the requisite thickness and amount of compaction.
Specifications.
Check the requirements for compaction,
thickness of layers, total thicknesses, and materials required for
each portion of the work. The drawings will also have to be checked
for some of these items.
The drawings will show the location of
most of the work to be completed, but the specifications should also
be checked. The specifications and drawings will list different
requirements for the various uses. (These are called traffic
requirements.)
Estimate.
The number of square feet (or square
yards) of surface area to be covered is determined, and the thickness
(compacted) of each course and the type of materials required are
noted. Base courses and the asphalt paving are often taken off by the
ton, as this is the unit in which these materials must be bought.
The type of asphalt and aggregate size
required must also be noted. Two layers of asphalt paving are
required on some projects: A coarse base mix may be used with a fine
topping mix. Equipment required may include a steel-wheel roller,
trailers to transport equipment, dump trucks, paving machines, and
various small tools.
To estimate the tons of material
required per 1,000 sf of surface area, refer to Figure 9.44.
Different requirements will be listed for the various uses (walk,
driveway, etc.), and the different spaces must be kept separately.
In many climates, the asphalt paving
has a cutoff date in cold weather, and the paving that is not placed
when the mixing plants shut down will not be laid until the start-up
time in the spring. The plants may be shut down for as long as four
months or more, depending on the locale.
FIGURE 9.44. Approximate Asphalt Paving
Materials Tonnage.

